Cal Water Update

Post Date:10/29/2019 10:37 AM
Take a look at the latest update from Cal Water on their ongoing pipeline project work:
  • Crews are making progress at the new pump station site on Crenshaw Boulevard, north of Silver Spur Road. Work is taking place from Monday to Friday, between 7:00 a.m. and 5:00 p.m. Traffic control is in place during work hours, with at least one lane of traffic open in each direction at all times.
  • Pipeline installation will continue on Crenshaw Boulevard this week, with two crews working near Crest Road and in the intersection of Crenshaw Boulevard and Crestridge Road, progressing north towards Palos Verdes Drive North. Work will take place from Monday to Friday, between 9 a.m. and 7:00 p.m. Please expect increased traffic delays as work continues and use alternate routes, like Hawthorne Boulevard, where possible.
  • As early as Tuesday, November 12, crews will begin nightwork on Crenshaw Boulevard, from north of Chadwick Lane to the South Coast Botanic Garden property, including the intersection of Crenshaw Boulevard and Palos Verdes Drive North. Construction in this area will take place from Monday to Friday, between 8:00 p.m. and 6:00 a.m., and is expected to last from approximately mid-November to January 2020.
For more information, please visit the  Map & Timeline  page at www.pvpwaterproject.com and follow the project on Facebook for ongoing updates. As a reminder, all construction timing is estimated and could change based on several factors, including unforeseeable field circumstances. Of note, CalWater recently made a change to the project team and are currently evaluating the sequence of construction to ensure timely completion. Project-related work is currently expected to continue until approximately mid-2020.
Thank you for your continued patience as CalWater works to bring this upgrade to the Peninsula.

 